Full Change Requests

Raise a Change Request on the full Change Request page, work through its reference documents by allocating new drawings and sheets or linking existing ones, and manage its folders, comments, and favourites.

Overview

The full Change Request page is Lunr's newer Change Request experience. It replaces the creation dialog with a full page, and adds an Overview tab, a Reference Documents tab, and a workflow progress nav across the top of the request.

This page covers the full experience from end to end. If your organisation gives you the standard Change Request instead, see Standard Change Requests. Introduction explains which one you have and how the two differ.

Change Requests are listed on a project's Change Requests tab, described in Working in a Project.

Raising a Change Request

Select New Change Request in the Action Pane of a project's Change Requests tab, which opens the creation page.

You can also raise one from the Create menu, including from the repository. Raising a request outside a project asks you to choose the project it belongs to, so you do not have to open the project first.

The page captures more than a subject and a message. Alongside those it takes attachments, tags, a priority and due date where those are enabled, and the reference documents the request asks for, and it can nominate a reviewer for each workflow stage. Everything on it can be edited afterwards, so nothing has to be final before you create the request.

Assigning Documents to a Change Request

Documents reach a Change Request in four ways.

  • Select them before raising the request.
  • Add them as reference documents, covered in Reference Documents below.
  • Upload them into the request. On the Documents tab, drag files onto the page, or use the Create menu in the Action Pane to create a document in the request. The same name-matching rules apply here as anywhere else, so an upload matching a document already in the request replaces its content, covered in Uploading Documents.
  • Assign existing documents to it. Select the documents anywhere in the repository or a project, then select Assign to Change Request in the More menu.

Assign to Change Request opens a dialog naming the documents you selected. Choose the project under Assign to project, then the request under Assign to Change Request. Leave the Change Request field empty, or enter a subject that matches no existing request, and Lunr creates a request with that subject and assigns the documents to it. The dialog confirms which of the two will happen before you submit, and warns you when a document already has child documents, since proceeding creates concurrent versions of it.

Assign to Change Request requires the Can Assign to Project access right, and is unavailable while only folders are selected.

Working a Change Request

A full Change Request opens on its Overview tab, which carries the request's details and its message. Documents, Reference Documents, Comments, and History sit alongside it, and Checklist joins them where checklists are enabled.

The header carries the request's status badge, an On Hold badge where it applies, and who opened the request and when, above a breadcrumb back to the project and its Change Requests list. Below it, the workflow progress nav shows the statuses the request passes through and how far along it is.

ActionWhat it does
CreateCreates a document directly in the request.
Request WorkflowMoves the request to its next status. It appears only where you have an action available, which depends on the request's current status, your access rights, and whether you are its creator, its assignee, or one of its reviewers. A request with validation issues offers no actions until they are resolved.
Place on Hold and ResumePauses a request awaiting external input and picks it up again, where your organisation has Change Request holds enabled.
Release All or Release SelectedReleases the request's valid documents, all of them or only those you have selected.
Download PackageDownloads the request's documents as a package.
Generate CR SummaryExports a PDF summary of the request.

Assigned To and Reviewers sit below, each listing the people currently on the request and reading "None yet" until someone is set. Where you can change them, a control beside the heading reassigns the request or its reviewers.

Where a workflow transition nominates its own reviewers, a Select Reviewer field appears for each one, offering the users eligible for that step alongside a Vendor option. A transition can mark its reviewer as required, shown by a red asterisk beside the field. A required field cannot be cleared, and leaving it empty reads "A reviewer must be selected." and holds the request until you choose someone.

Selecting documents in the list switches the lower part of the panel to batch actions covering the selection, including updating tags, transitioning documents through their own workflow, sharing, exporting, and Discard from CR.

Reference Documents

The Reference Documents page lists the changes the request asks for. Each line carries a change type, which decides how the line is processed. Working a request means processing those lines until every change has either produced a new document or been linked to an existing one.

Change typeWhat it asks forHow it is processed
NEW DWGA new drawingAllocation
NEW SHTNew sheets on a drawingAllocation
NEW DWG+SHTA new drawing and its sheetsAllocation
REVISIONA new revision of an existing drawingChild linking
SUPERSEDEAn existing drawing supersededChild linking
OBSOLETEAn existing drawing made obsoleteChild linking

Lines that raise something new are processed by allocating a document from a repository template. Lines that act on a drawing already in the repository are processed by linking a child document to it.

Documents already in the repository are added as reference documents by selecting them, then choosing Add as Reference Documents in the More menu.

Allocating New Drawings and Sheets

Select Bulk Allocate in the toolbar to allocate every line waiting for allocation in one action, rather than working through them one at a time. To allocate a single line instead, select Process on that row.

Both routes open the same Bulk Allocate Reference Documents dialog, which works in two steps.

  1. Under Configuration, choose the Template the placeholder documents are created from. This is required. Optionally choose a Target Folder; leave it blank to use the Change Request's default folder.
  2. Check the lines under Documents to Allocate and anything reported under Tag Requirements. Where a line is missing a tag it needs, select the edit action on that line to supply it.
  3. Select Preview to see what the allocation will produce.
  4. Select Confirm to allocate, or Back to change the configuration first. The button reads "Allocating..." while it runs.

Lunr reports what it allocated when the run finishes, including any lines it skipped because they were already allocated.

Allocating a reference document releases the new document as a master, so it requires both the Release as Master access right and reviewer standing on this Change Request. Bulk Allocate does not appear without them.

Partly Allocated Lines

A line asking for a batch of sheets can be allocated more than once. A row shows how many of its requested sheets have been allocated, as a fraction, and an already-allocated sheet title can no longer be changed.

Raising a line's quantity after it has been allocated brings it back into the list, so a later run allocates only the extra sheets rather than repeating the ones already done.

Linking Existing Drawings

A REVISION, SUPERSEDE, or OBSOLETE line is processed by linking a child document to the repository drawing it names, so the line cannot be processed until that drawing has been chosen.

Linking requires the Fork Documents and Can Assign to Project access rights, along with involvement in this Change Request as its creator, its assignee, one of its reviewers, or the manager of its project. The Manage Projects access right grants it regardless of involvement.

Change Request Folders

Where your organisation enables Change Request folders, a request can hold folders of its own.

A Change Request folder starts closed, visible only to the members assigned to it rather than to everyone on the request. This is the opposite of a project folder, which starts open, so check folder membership if you expect the whole request to see a folder's documents.

Comments

Anyone who can open a Change Request can comment on it. You do not need to be its creator, its assignee, or one of its reviewers.

Favourites

Select the star on a Change Request row to favourite it, and it appears in your favourites for quick access. A request that closes, meaning it reached Complete or Cancelled, drops out of your favourites list, though its star still shows on the request's own page so you can clear it. A rejected request is not closed and stays in the list, since it can be updated and resubmitted.

Finding Change Requests

The Change Requests tab offers a search field, a Filter button, an "Open | Closed" summary, an Export button, and a Sort dropdown. The filters include one for requests with validation issues, which narrows the list to the requests whose documents have them.